Case Study – LM2500 Gas Turbine Installation
Challenge: Integrating multiple auxiliary systems while ensuring safety, reliability, and compliance. Risks included hydraulic instability, poor venting, and late- stage design changes.
Approach:
-Full system review including starter, fire fighting, water wash, fuel and diesel systems
- Accurate LM2500 fuel consumption calculations
- Safe and optimized diesel day tank design
- Proper hydraulic and piping design including vent, drain and overflow systems

Key Engineering Focus:
- Stable flow and correct pipe sizing
- Overfill protection and drainage design
- 3-hour full load fuel capacity
- Reliable operation under real conditions
Deliverables: PFD, P&IDs, Equipment Datasheet, Calculations, HAZOP & LOPA support
Results:
- Reliable system integration
- Improved safety and compliance
- Reduced design risk and rework
- Lower lifecycle cost
Value: Smart process engineering ensures long-term performance, cost savings, and reliable operation.
Contact: Available to support gas turbine and modular skid projects